USA Fiber has put the final touches on its Ashburn Ring Conduit System, a 7.3-mile network targeting the needs of the Ashburn, Va., data center market.
What’s interesting about this buildout is the time it took to complete it: just 138 days to complete the multi-conduit system. USA Fiber said that only 75 of those days were active, with no construction work being done on 63 days due to weekends, holidays and weather